ITAC Assessment: AT0038
ITAC logo
ITAC Assessment: AT0038
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product POTATO CHIPS
NAICS
n/a
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 14
Plant Area
n/a
Annual Production 1,400,000
lb
Production Hrs. Annual 2,080
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $6,443 79,132
kWh
Natural Gas $28,964 5,387
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,901 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $33 $32 $33
293
kWh
-
02 2.2444: Use hot process fluids to preheat incoming process fluids $2,018 $4,000 - $2,018
-
MMBtu
03 2.7142: Utilize higher efficiency lamps and/or ballasts $48 $18 $48
586
kWh
-
04 2.2511: Insulate bare equipment $140 $150 - $140
-
MMBtu
05 2.4231: Reduce the pressure of compressed air to the minimum required $95 - $95
1,172
kWh
-
06 2.2449: Recover heat from exhausted steam, hot air or hot water $1,567 $985 - $1,567
-
MMBtu
TOTAL RECOMMENDED $3,901 $5,185 $176
2,051
kWh
$3,725
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs