| Assessment Year | 2022 |
|---|---|
| Principal Product | Residential Framing |
| NAICS | 321214: Truss Manufacturing |
| SIC | 2439: Structural Wood Members, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 394 |
| Plant Area |
208,077
ft2
|
| Annual Production | 2,800
units
|
| Production Hrs. Annual | 8,472
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $71,738 | 927,840 |
kWh
|
$0.077 |
| Electricity Demand | $14,207 | 3,305 |
kW-mo/yr
|
$4.30 |
| Electricity Fees | $8,977 | - |
|
- |
| Fuel Oil #1 | $288,488 | 11,931 |
MMBtu
|
$24.18 |
| TOTAL YEARLY COSTS | $383,410 | |||
| RECOMMENDED SAVINGS* | $234,949 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $183,385 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #1 Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.5313: Increase amount of waste recovered for resale | $125,792 | $20,098 |
$(-40,380.0)
(-521,028)
kWh
|
$(-3,070.0)
-
kW-mo/yr
|
- | - | $(-412,502.0) | - | - | $581,744 | |
| 02 | 2.1321: Replace fossil fuel equipment with electrical equipment | $30,224 | $146,764 |
$(-11,236.0)
(-144,978)
kWh
|
- | - |
$41,460
-
MMBtu
|
- | - | - | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $21,340 | $9,935 |
$19,225
248,065
kWh
|
$2,115
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,528 | $28,033 |
$18,317
236,354
kWh
|
$861
-
kW-mo/yr
|
- | - | - | $(-650.0) | - | - | |
| 05 | 2.9114: Use solar heat to make electricty | $6,571 | $72,520 |
$5,963
77,150
kWh
|
$608
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 06 | 2.8121: Apply for tax-free status for energy purchases | $27,420 | $500 | - | - | $5,484 | - | - | - | $21,936 | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,242 | $7,928 |
$3,014
38,886
kWh
|
$228
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 08 | 2.7135: Install occupancy sensors | $1,832 | $3,388 |
$1,832
23,634
kWh
|
- | - | - | - | - | - | - | |
| TOTAL RECOMMENDED | $234,949 | $289,166 |
$(-3,265.0)
(-41,917)
kWh
|
$742
-
kW-mo/yr
|
$5,484 |
$41,460
-
MMBtu
|
$(-412,502.0) | $(-650.0) | $21,936 | $581,744 | ||
| TOTAL IMPLEMENTED | $183,385 | $132,467 |
$(-11,254.0)
(-145,004)
kWh
|
$(-1,373.0)
-
kW-mo/yr
|
$5,484 | - | $(-412,502.0) | $(-650.0) | $21,936 | $581,744 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #1 Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs