ITAC Assessment: AS0463
ITAC logo
ITAC Assessment: AS0463
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Fluid Milk
NAICS 311511: Fluid Milk Manufacturing
SIC 2026: Fluid Milk
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 40,000
ft2
Annual Production 1,600
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $117,952 2,891,220
kWh
Electricity Demand $107,031 6,915
kW-mo/yr
Electricity Fees $50,555 -
Natural Gas $101,244 13,086
MMBtu
Fuel Oil #1 $1,626,217 52,724
MMBtu
Waste Disposal Costs
Water Usage $228,404 3,855
Tgal
TOTAL YEARLY COSTS $2,231,403
RECOMMENDED SAVINGS* $116,359 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $65,615

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #1 Savings
01 2.8223: Add air shields to trucks to increase fuel mileage $56,524 $90,000 - - - $56,524
-
MMBtu
02 2.4231: Reduce the pressure of compressed air to the minimum required $31,405 $2,867 $20,666
506,509
kWh
$10,739
-
kW-mo/yr
- -
03 2.8226: Increase efficiency of trucks $11,257 $18,720 - - - $11,257
-
MMBtu
04 2.1243: Use heat from boiler blowdown to preheat boiler feed water $8,082 $3,232 - - $8,082
-
MMBtu
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $6,693 - $4,404
107,944
kWh
$2,289
-
kW-mo/yr
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,398 $6,295 $1,828
44,803
kWh
$570
-
kW-mo/yr
- -
TOTAL RECOMMENDED $116,359 $121,114 $26,898
659,256
kWh
$13,598
-
kW-mo/yr
$8,082
-
MMBtu
$67,781
-
MMBtu
TOTAL IMPLEMENTED $65,615 $96,295 $6,232
152,747
kWh
$2,859
-
kW-mo/yr
- $56,524
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #1 Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs