| Assessment Year | 2005 |
|---|---|
| Principal Product | Wood products |
| NAICS | 321113: Sawmills |
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | $10 M to 50M |
| # of Employees | 245 |
| Plant Area |
871,200
ft2
|
| Annual Production | 43,000
thousand feet
|
| Production Hrs. Annual | 2,448
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $297,057 | 14,282,640 |
kWh
|
$0.021 |
| Electricity Demand | $452,466 | 69,937 |
kW-mo/yr
|
$6.47 |
| Electricity Fees | $65,381 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $1,016,564 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,000 | $2,000 |
$9,991
475,783
kWh
|
$1,009
-
kW-mo/yr
|
- | |
| 02 | 2.3212: Optimize plant power factor | $749,532 | $6,404,000 |
$297,060
14,282,400
kWh
|
$452,472
-
kW-mo/yr
|
- | |
| 03 | 2.4133: Use most efficient type of electric motors | $2,293 | $2,902 |
$845
40,256
kWh
|
$1,448
-
kW-mo/yr
|
- | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $811 | - |
$299
14,223
kWh
|
$512
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,184 | $4,984 |
$436
20,770
kWh
|
$748
-
kW-mo/yr
|
- | |
| 06 | 4.642: Install sensors to detect and avoid jams | $251,744 | $8,000 | - | - | $251,744 | |
| TOTAL RECOMMENDED | $1,016,564 | $6,421,886 |
$308,631
14,833,432
kWh
|
$456,189
-
kW-mo/yr
|
$251,744 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs