ITAC Assessment: AS0398
ITAC logo
ITAC Assessment: AS0398
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Wood products
NAICS 321113: Sawmills
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 245
Plant Area 871,200
ft2
Annual Production 43,000
thousand feet
Production Hrs. Annual 2,448
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $297,057 14,282,640
kWh
Electricity Demand $452,466 69,937
kW-mo/yr
Electricity Fees $65,381 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,016,564 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Primary Product Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $11,000 $2,000 $9,991
475,783
kWh
$1,009
-
kW-mo/yr
-
02 2.3212: Optimize plant power factor $749,532 $6,404,000 $297,060
14,282,400
kWh
$452,472
-
kW-mo/yr
-
03 2.4133: Use most efficient type of electric motors $2,293 $2,902 $845
40,256
kWh
$1,448
-
kW-mo/yr
-
04 2.7111: Reduce illumination to minimum necessary levels $811 - $299
14,223
kWh
$512
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,184 $4,984 $436
20,770
kWh
$748
-
kW-mo/yr
-
06 4.642: Install sensors to detect and avoid jams $251,744 $8,000 - - $251,744
TOTAL RECOMMENDED $1,016,564 $6,421,886 $308,631
14,833,432
kWh
$456,189
-
kW-mo/yr
$251,744
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs