ITAC Assessment: AS0339
ITAC logo
ITAC Assessment: AS0339
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Gravel and Sand
NAICS
n/a
SIC 3273: Ready-Mixed Concrete
Sales Range $1
M
to 5
M
# of Employees 10
Plant Area 21,780,000
ft2
Annual Production 750,000
ton
Production Hrs. Annual 4,048
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Other Gas $128,345 18,455
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $199,224 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $113,559

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Other Gas Savings Primary Product Savings
01 2.2426: Use waste heat from flue gases to heat space conditioning air $393 $1,000 $393
-
MMBtu
-
02 2.4133: Use most efficient type of electric motors $286 $314 $286
-
MMBtu
-
03 2.3212: Optimize plant power factor $45,235 $1,540 $45,235
-
MMBtu
-
04 4.111: Add equipment/ operators to reduce production bottleneck $113,273 $9,000 - $113,273
05 4.445: Install equipment to move product $40,037 $40,000 $40,037
-
MMBtu
-
TOTAL RECOMMENDED $199,224 $51,854 $85,951
-
MMBtu
$113,273
TOTAL IMPLEMENTED $113,559 $9,314 $286
-
MMBtu
$113,273
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs