Assessment Year | 2002 |
---|---|
Principal Product | Gravel and Sand |
NAICS |
n/a
|
SIC | 3273: Ready-Mixed Concrete |
Sales Range | $1 M to 5M |
# of Employees | 10 |
Plant Area |
21,780,000
ft2
|
Annual Production | 750,000
ton
|
Production Hrs. Annual | 4,048
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Other Gas | $128,345 | 18,455 |
MMBtu
|
$6.95 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $199,224 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $113,559 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Other Gas Savings | Primary Product Savings |
---|---|---|---|---|---|---|
01 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $393 | $1,000 |
$393
-
MMBtu
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $286 | $314 |
$286
-
MMBtu
|
- | |
03 | 2.3212: Optimize plant power factor | $45,235 | $1,540 |
$45,235
-
MMBtu
|
- | |
04 | 4.111: Add equipment/ operators to reduce production bottleneck | $113,273 | $9,000 | - | $113,273 | |
05 | 4.445: Install equipment to move product | $40,037 | $40,000 |
$40,037
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $199,224 | $51,854 |
$85,951
-
MMBtu
|
$113,273 | ||
TOTAL IMPLEMENTED | $113,559 | $9,314 |
$286
-
MMBtu
|
$113,273 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs