| Assessment Year | 2002 |
|---|---|
| Principal Product | Concrete |
| NAICS |
n/a
|
| SIC | 3273: Ready-Mixed Concrete |
| Sales Range | $5 M to 10M |
| # of Employees | 45 |
| Plant Area |
283,140
ft2
|
| Annual Production | 192,000
units
|
| Production Hrs. Annual | 4,298
hrs
|
| Location (State) | Nevada |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $36,170 | 463,350 |
kWh
|
$0.078 |
| Electricity Demand | $3,867 | 1,328 |
kW-mo/yr
|
$2.91 |
| Electricity Fees | $2,187 | - |
|
- |
| Other Gas | $380,000 | 60,000 |
MMBtu
|
$6.33 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $22,982 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,270 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $392 | $1,387 |
$357
4,350
kWh
|
$35
-
kW-mo/yr
|
- | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $281 | - |
$255
3,110
kWh
|
$26
-
kW-mo/yr
|
- | |
| 03 | 2.6218: Turn off equipment when not in use | $395 | $1,422 |
$395
4,814
kWh
|
- | - | |
| 04 | 2.1224: Replace boiler | $1,014 | $2,300 |
$1,014
160
kWh
|
- | - | |
| 05 | 2.7232: Replace existing hvac unit with high efficiency model | $875 | $2,400 |
$831
10,131
kWh
|
$44
-
kW-mo/yr
|
- | |
| 06 | 4.445: Install equipment to move product | $20,025 | $38,900 | - | - | $20,025 | |
| TOTAL RECOMMENDED | $22,982 | $46,409 |
$2,852
22,565
kWh
|
$105
-
kW-mo/yr
|
$20,025 | ||
| TOTAL IMPLEMENTED | $1,270 | $3,822 |
$1,226
14,945
kWh
|
$44
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs