ITAC Assessment: AS0315
ITAC logo
ITAC Assessment: AS0315
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Paint
NAICS
n/a
SIC 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products
Sales Range $1
M
to 5
M
# of Employees 32
Plant Area 208,000
ft2
Annual Production 264
Tgal
Production Hrs. Annual 2,142
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $22,123 345,628
kWh
Electricity Demand $3,993 1,802
kW-mo/yr
Electricity Fees $3,102 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,212 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.4314: Use synthetic lubricant $221 $174 $124
2,204
kWh
$72
-
kW-mo/yr
$25
-
gal
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,749 $7,491 $1,136
20,239
kWh
$613
-
kW-mo/yr
- - -
03 2.7135: Install occupancy sensors $105 $525 $105
1,868
kWh
- - - -
04 4.521: Clear and rent existing space $32,448 $3,360 - - - - $32,448
05 4.322: Eliminate old stock and modify inventory control $81 $306 - - - - $81
06 4.445: Install equipment to move product $2,608 $1,832 - - - $2,608 -
TOTAL RECOMMENDED $37,212 $13,688 $1,365
24,311
kWh
$685
-
kW-mo/yr
$25
-
gal
$2,608 $32,529
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs