Assessment Year | 2001 |
---|---|
Principal Product | Paint |
NAICS |
n/a
|
SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
Sales Range | $1 M to 5M |
# of Employees | 32 |
Plant Area |
208,000
ft2
|
Annual Production | 264
Tgal
|
Production Hrs. Annual | 2,142
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $22,123 | 345,628 |
kWh
|
$0.064 |
Electricity Demand | $3,993 | 1,802 |
kW-mo/yr
|
$2.22 |
Electricity Fees | $3,102 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $37,212 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4314: Use synthetic lubricant | $221 | $174 |
$124
2,204
kWh
|
$72
-
kW-mo/yr
|
$25
-
gal
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,749 | $7,491 |
$1,136
20,239
kWh
|
$613
-
kW-mo/yr
|
- | - | - | |
03 | 2.7135: Install occupancy sensors | $105 | $525 |
$105
1,868
kWh
|
- | - | - | - | |
04 | 4.521: Clear and rent existing space | $32,448 | $3,360 | - | - | - | - | $32,448 | |
05 | 4.322: Eliminate old stock and modify inventory control | $81 | $306 | - | - | - | - | $81 | |
06 | 4.445: Install equipment to move product | $2,608 | $1,832 | - | - | - | $2,608 | - | |
TOTAL RECOMMENDED | $37,212 | $13,688 |
$1,365
24,311
kWh
|
$685
-
kW-mo/yr
|
$25
-
gal
|
$2,608 | $32,529 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs