ITAC Assessment: AS0310
ITAC logo
ITAC Assessment: AS0310
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Prefabricated Houses and Wood Buildings
NAICS
n/a
SIC 2452: Prefabricated Wood Buildings and Components
Sales Range $5
M
to 10
M
# of Employees 35
Plant Area 55,000
ft2
Annual Production 694
units
Production Hrs. Annual 2,268
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $4,950 79,680
kWh
Electricity Demand $688 324
kW-mo/yr
Electricity Fees $875 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $104,520 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,068

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Primary Raw Material Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $834 $2,736 $543
9,725
kWh
$291
-
kW-mo/yr
- -
02 2.7135: Install occupancy sensors $91 $450 $63
1,132
kWh
$28
-
kW-mo/yr
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $68 $60 $22
386
kWh
$46
-
kW-mo/yr
- -
04 2.7232: Replace existing hvac unit with high efficiency model $533 $1,400 $403
7,234
kWh
$130
-
kW-mo/yr
- -
05 4.711: Initiate a total quality management program $12,000 $3,100 - - $12,000 -
06 4.513: Re-arrange equipment layout to reduce labor costs $54,594 $2,880 - - $54,594 -
07 4.514: Re-arrange equipment layout to reduce handling costs $36,400 $10,400 - - - $36,400
TOTAL RECOMMENDED $104,520 $21,026 $1,031
18,477
kWh
$495
-
kW-mo/yr
$66,594 $36,400
TOTAL IMPLEMENTED $12,068 $3,160 $22
386
kWh
$46
-
kW-mo/yr
$12,000 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs