Assessment Year | 2001 |
---|---|
Principal Product | Residential Glass Windows and Patio Doors |
NAICS |
n/a
|
SIC | 3231: Glass Products, Made of Purchased Glass |
Sales Range | $10 M to 50M |
# of Employees | 330 |
Plant Area |
225,000
ft2
|
Annual Production | 350,000
pieces
|
Production Hrs. Annual | 5,912
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $229,746 | 3,943,440 |
kWh
|
$0.058 |
Electricity Demand | $27,541 | 10,532 |
kW-mo/yr
|
$2.61 |
Electricity Fees | $20,302 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $337,070 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7145: Install skylights | $2,313 | $9,960 | n/a |
$2,313
58,032
kWh
|
- | - | - | - | - |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $500 | $60 | n/a |
$302
7,567
kWh
|
$198
-
kW-mo/yr
|
- | - | - | - |
03 | 2.7135: Install occupancy sensors | $418 | $1,425 | n/a |
$184
4,607
kWh
|
$234
-
kW-mo/yr
|
- | - | - | - |
04 | 2.4133: Use most efficient type of electric motors | $98 | $89 | n/a |
$59
1,484
kWh
|
$39
-
kW-mo/yr
|
- | - | - | - |
05 | 3.4155: Meter waste water | $11,634 | $1,300 | n/a | - | - |
$11,634
-
Tgal
|
- | - | - |
06 | 3.6192: Use a less expensive method of waste removal | $1,620 | $60 | n/a | - | - | - | - | $1,620 | - |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $2,604 | $60 | n/a | - | - | - | - | $2,604 | - |
08 | 2.8114: Change rate schedules or other changes in utility service | $240 | $30 | n/a | - | - | - | - | $240 | - |
09 | 4.122: Develop standard procedures to improve internal yields | $37,500 | $456 | n/a | - | - | - | - | - | $37,500 |
10 | 4.511: Expand operations into unused space | $280,143 | $6,204 | n/a | - | - | - | $280,143 | - | - |
TOTAL RECOMMENDED | $337,070 | $19,644 |
$2,858
71,690
kWh
|
$471
-
kW-mo/yr
|
$11,634
-
Tgal
|
$280,143 | $4,464 | $37,500 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs