ITAC Assessment: AS0281
ITAC logo
ITAC Assessment: AS0281
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Aerospace Fasteners
NAICS
n/a
SIC 3452: Bolts, Nuts, Screws, Rivets, and Washers
Sales Range $10
M
to 50
M
# of Employees 160
Plant Area 70,000
ft2
Annual Production 1,800,000
pieces
Production Hrs. Annual 5,683
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $369,659 5,857,855
kWh
Electricity Demand $94,152 13,561
kW-mo/yr
Electricity Fees $23,906 -
Natural Gas $29,374 4,539
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $65,025 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,493

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings By-product Production Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $895 $2,709 $739
11,137
kWh
$156
-
kW-mo/yr
- - - - -
02 2.7121: Utilize daylight whenever possible in lieu of artificial light $581 $600 $581
9,672
kWh
- - - - - -
03 2.4133: Use most efficient type of electric motors $2,825 $3,713 $2,312
35,170
kWh
$513
-
kW-mo/yr
- - - - -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,723 $4,950 $7,192
109,027
kWh
$531
-
kW-mo/yr
- - - - -
05 3.3131: Use evaporation to concentrate material $8,037 $8,525 - - $(-7,509.0)
-
MMBtu
$56,975
-
gal
- $(-41,429.0) -
06 3.6192: Use a less expensive method of waste removal $456 $60 - - - - $456
-
lb
- -
07 3.6192: Use a less expensive method of waste removal $4,476 $60 - - - - $(-204.0)
-
lb
- $4,680
08 4.454: Modify startup/shutdown times $8,782 $9,600 - $8,782
-
kW-mo/yr
- - - - -
09 4.111: Add equipment/ operators to reduce production bottleneck $31,250 $15,000 - - - - - $31,250 -
TOTAL RECOMMENDED $65,025 $45,217 $10,824
165,006
kWh
$9,982
-
kW-mo/yr
$(-7,509.0)
-
MMBtu
$56,975
-
gal
$252
-
lb
$(-10,179.0) $4,680
TOTAL IMPLEMENTED $8,493 $8,585 - - $(-7,509.0)
-
MMBtu
$56,975
-
gal
$456
-
lb
$(-41,429.0) -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs