Assessment Year | 1999 |
---|---|
Principal Product | Diffusers and Air Handlers |
NAICS |
n/a
|
SIC | 3444: Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 470 |
Plant Area |
262,000
ft2
|
Annual Production | 2,000,000
ton
|
Production Hrs. Annual | 5,900
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $336,772 | 4,820,047 |
kWh
|
$0.070 |
Electricity Demand | $78,307 | 12,648 |
kW-mo/yr
|
$6.19 |
Electricity Fees | $36,636 | - |
|
- |
Natural Gas | $141,156 | 24,596 |
MMBtu
|
$5.74 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $49,473 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,135 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $689 | $696 |
$401
5,862
kWh
|
$58
-
kW-mo/yr
|
- | $114 | $116 | |
02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $7,274 | $1,040 |
$7,274
104,924
kWh
|
- | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,741 | $120 |
$7,585
109,613
kWh
|
$1,156
-
kW-mo/yr
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,394 | $1,000 |
$12,687
183,177
kWh
|
$2,707
-
kW-mo/yr
|
- | - | - | |
05 | 3.6192: Use a less expensive method of waste removal | $720 | $30 | - | - |
$720
-
lb
|
- | - | |
06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $14,688 | $12,256 | - | - |
$14,688
-
lb
|
- | - | |
07 | 4.111: Add equipment/ operators to reduce production bottleneck | $1,967 | $180 | - | - | - | $1,967 | - | |
TOTAL RECOMMENDED | $49,473 | $15,322 |
$27,947
403,576
kWh
|
$3,921
-
kW-mo/yr
|
$15,408
-
lb
|
$2,081 | $116 | ||
TOTAL IMPLEMENTED | $24,135 | $1,120 |
$20,272
292,790
kWh
|
$3,863
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs