Assessment Year | 2024 |
---|---|
Principal Product | Commercial grade fountain equipment |
NAICS | 332919: Other Metal Valve and Pipe Fitting Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
60,000
ft2
|
Annual Production | 7,000
units
|
Production Hrs. Annual | 2,241
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $57,639 | 738,033 |
kWh
|
$0.078 |
Electricity Demand | $12,086 | 2,417 |
kW-mo/yr
|
$5.00 |
Electricity Fees | $8,220 | - |
|
- |
Other Gas | $29,175 | 1,011 |
MMBtu
|
$28.86 |
TOTAL YEARLY COSTS | $107,120 | |||
RECOMMENDED SAVINGS* | $54,385 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Gas Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $30,000 | $10,000 | - | - | $6,000 | - | - | $24,000 | |
02 | 2.2531: Re-size charging openings or add movable cover or door | $16,800 | $21,600 | - | - | - |
$16,800
-
MMBtu
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,600 | $8,190 |
$2,500
32,500
kWh
|
$850
-
kW-mo/yr
|
- | - | $250 | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,170 | $550 |
$1,600
21,300
kWh
|
$570
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7135: Install occupancy sensors | $1,070 | $2,100 |
$1,070
13,700
kWh
|
- | - | - | - | - | |
06 | 2.7132: Install timers on light switches in little used areas | $385 | $680 |
$330
4,200
kWh
|
$55
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $360 | $970 |
$360
4,600
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $54,385 | $44,090 |
$5,860
76,300
kWh
|
$1,475
-
kW-mo/yr
|
$6,000 |
$16,800
-
MMBtu
|
$250 | $24,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Gas Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs