ITAC Assessment: AM0869
ITAC logo
ITAC Assessment: AM0869
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product retailer that specializes in hunting, fishing, boating, camping, shooting and other outdoor recreation merchandise
NAICS 423910: Sporting and Recreational Goods and Supplies Merchant Wholesalers
SIC 5091: Sporting and Recreational Goods and Supplies
Sales Range $5
M
to 10
M
# of Employees 100
Plant Area 232,000
ft2
Annual Production 100,000
units
Production Hrs. Annual 5,616
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $207,005 5,112,000
kWh
Electricity Demand $98,640 9,864
kW-mo/yr
Natural Gas $8,517 477
MMBtu
Waste Disposal Costs
Water Usage $51,042 3,433
Tgal
TOTAL YEARLY COSTS $365,204
RECOMMENDED SAVINGS* $135,660 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $21,141 $137,722 $14,631
311,294
kWh
$6,510
-
kW-mo/yr
02 2.9114: Use solar heat to make electricty $57,664 $468,000 $21,664
460,929
kWh
$36,000
-
kW-mo/yr
03 2.7232: Replace existing hvac unit with high efficiency model $56,855 $1,012,500 $23,272
495,145
kWh
$33,583
-
kW-mo/yr
TOTAL RECOMMENDED $135,660 $1,618,222 $59,567
1,267,368
kWh
$76,093
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs