Assessment Year | 2022 |
---|---|
Principal Product | Sanitized waste water |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $10 M to 50M |
# of Employees | 15 |
Plant Area |
292,545
ft2
|
Annual Production | 912,500
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $182,772 | 4,536,626 |
kWh
|
$0.040 |
Electricity Demand | $73,104 | 9,910 |
kW-mo/yr
|
$7.38 |
Electricity Fees | $8,745 | - |
|
- |
TOTAL YEARLY COSTS | $264,621 | |||
RECOMMENDED SAVINGS* | $99,716 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $99,716 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 3.1191: Change procedures / equipment / operating conditions | $50,900 | $9,100 |
$50,900
1,264,000
kWh
|
- | - | |
02 | 3.1191: Change procedures / equipment / operating conditions | $33,965 | $13,500 |
$26,300
653,500
kWh
|
$7,665
-
kW-mo/yr
|
- | |
03 | 2.3212: Optimize plant power factor | $9,077 | $27,090 | - |
$9,077
-
kW-mo/yr
|
- | |
04 | 2.8123: Pay utility bills on time | $1,114 | - | - | - | $1,114 | |
05 | 2.7135: Install occupancy sensors | $649 | $360 |
$649
16,096
kWh
|
- | - | |
06 | 2.4314: Use synthetic lubricant | $302 | $700 |
$252
6,259
kWh
|
$50
-
kW-mo/yr
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,709 | $15,704 |
$2,421
60,084
kWh
|
$1,288
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $99,716 | $66,454 |
$80,522
1,999,939
kWh
|
$18,080
-
kW-mo/yr
|
$1,114 | ||
TOTAL IMPLEMENTED | $99,716 | $66,454 |
$80,522
1,999,939
kWh
|
$18,080
-
kW-mo/yr
|
$1,114 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs