| Assessment Year | 2018 |
|---|---|
| Principal Product | Compressor rings and gaskets |
| NAICS | 339991: Gasket, Packing, and Sealing Device Manufacturing |
| SIC | 3053: Gaskets, Packing, and Sealing Devices |
| Sales Range | $10 M to 50M |
| # of Employees | 40 |
| Plant Area |
70,000
ft2
|
| Annual Production | 500,000
lb
|
| Production Hrs. Annual | 2,380
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $86,209 | 2,045,221 |
kWh
|
$0.042 |
| Electricity Demand | $64,679 | 5,499 |
kW-mo/yr
|
$11.76 |
| Electricity Fees | $3,254 | - |
|
- |
| Natural Gas | $40,288 | 5,026 |
MMBtu
|
$8.02 |
| TOTAL YEARLY COSTS | $194,430 | |||
| RECOMMENDED SAVINGS* | $38,900 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $17,280 | $17,230 | - |
$17,280
-
kW-mo/yr
|
- | - | |
| 02 | 2.8121: Apply for tax-free status for energy purchases | $13,320 | $2,000 | - | - | $2,664 | $10,656 | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,120 | $1,000 |
$1,060
26,180
kWh
|
$2,060
-
kW-mo/yr
|
- | - | |
| 04 | 2.6218: Turn off equipment when not in use | $3,100 | - |
$3,100
76,300
kWh
|
- | - | - | |
| 05 | 2.7124: Make a practice of turning off lights when not needed | $1,260 | - |
$1,260
31,100
kWh
|
- | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $820 | $3,460 |
$820
20,230
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $38,900 | $23,690 |
$6,240
153,810
kWh
|
$19,340
-
kW-mo/yr
|
$2,664 | $10,656 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs