Assessment Year | 2018 |
---|---|
Principal Product | Aluminum roof covers |
NAICS | 332312: Fabricated Structural Metal Manufacturing |
SIC | 3441: Fabricated Structural Metal |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
57,000
ft2
|
Annual Production | 500
units
|
Production Hrs. Annual | 8,496
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $92,908 | 1,582,848 |
kWh
|
$0.059 |
Electricity Demand | $24,978 | 3,664 |
kW-mo/yr
|
$6.82 |
Electricity Fees | $1,831 | - |
|
- |
Natural Gas | $268 | 31 |
MMBtu
|
$8.65 |
TOTAL YEARLY COSTS | $119,985 | |||
RECOMMENDED SAVINGS* | $35,275 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $32,402 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $28,380 | $23,100 |
$23,830
397,100
kWh
|
$4,550
-
kW-mo/yr
|
- | |
02 | 2.3212: Optimize plant power factor | $1,820 | $2,560 | - |
$1,820
-
kW-mo/yr
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,760 | $16 |
$1,500
25,000
kWh
|
$260
-
kW-mo/yr
|
- | |
04 | 2.4239: Eliminate or reduce compressed air usage | $920 | $430 |
$920
15,300
kWh
|
- | - | |
05 | 2.8123: Pay utility bills on time | $1,277 | - | - | - | $1,277 | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $735 | $500 |
$625
10,400
kWh
|
$110
-
kW-mo/yr
|
- | |
07 | 2.7124: Make a practice of turning off lights when not needed | $250 | - |
$250
4,160
kWh
|
- | - | |
08 | 4.821: Pay bills on time to avoid late fees | $133 | $33 | - | - | $133 | |
TOTAL RECOMMENDED | $35,275 | $26,639 |
$27,125
451,960
kWh
|
$6,740
-
kW-mo/yr
|
$1,410 | ||
TOTAL IMPLEMENTED | $32,402 | $23,616 |
$26,205
436,660
kWh
|
$4,920
-
kW-mo/yr
|
$1,277 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs