ITAC Assessment: AM0646
ITAC logo
ITAC Assessment: AM0646
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Lighting fixtures
NAICS 335129: Other Lighting Equipment Manufacturing
SIC 3648: Lighting Equipment, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 380
Plant Area 292,000
ft2
Annual Production 2,554,090
pieces
Production Hrs. Annual 2,100
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $390,084 5,758,400
kWh
Electricity Demand $82,465 14,341
kW-mo/yr
Electricity Fees $12,888 -
Natural Gas $66,689 11,800
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $122,175 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,970

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $49,500 $242,900 $32,100
472,500
kWh
$15,500
-
kW-mo/yr
- - $300 $1,600
02 4.132: Purchase new equipment to reduce material use / cost $42,430 $14,500 - - - - - $42,430
03 3.4116: Meter recycled water (to reduce sewer charges) $10,300 $300 - - $10,300
-
Tgal
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $7,470 $2,800 $5,000
73,250
kWh
$2,400
-
kW-mo/yr
- - $70 -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $3,610 $2,250 $680
10,000
kWh
$80
-
kW-mo/yr
- - $1,100 $1,750
06 2.1117: Relocate oven / furnace to more efficient location $2,505 $5,010 $1,690
24,845
kWh
$815
-
kW-mo/yr
- - - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,850 $500 $1,920
28,275
kWh
$930
-
kW-mo/yr
- - - -
08 2.4239: Eliminate or reduce compressed air usage $1,470 $770 $1,470
21,600
kWh
- - - - -
09 2.4231: Reduce the pressure of compressed air to the minimum required $1,385 - $935
13,740
kWh
$450
-
kW-mo/yr
- - - -
10 3.5248: Separate and recycle scrap metal to foundry or for sale $440 - - - - $440
-
lb
- -
11 2.4314: Use synthetic lubricant $215 - $145
2,136
kWh
$70
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $122,175 $269,030 $43,940
646,346
kWh
$20,245
-
kW-mo/yr
$10,300
-
Tgal
$440
-
lb
$1,470 $45,780
TOTAL IMPLEMENTED $9,970 $3,520 $5,150
75,751
kWh
$1,530
-
kW-mo/yr
- $440
-
lb
$1,100 $1,750
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs