ITAC Assessment: AM0631
ITAC logo
ITAC Assessment: AM0631
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Flexible packaging
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 100,000
ft2
Annual Production 240,000
thousand feet
Production Hrs. Annual 5,952
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $479,482 8,748,688
kWh
Electricity Demand $117,358 17,616
kW-mo/yr
Electricity Fees $41,480 -
Natural Gas $203,450 54,324
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $189,630 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings One-time Revenue or Avoided Cost Savings
01 2.8121: Apply for tax-free status for energy purchases $166,700 $10,000 - - $33,360 $133,340
02 2.7124: Make a practice of turning off lights when not needed $10,080 - $8,330
170,100
kWh
$1,750
-
kW-mo/yr
- -
03 2.3212: Optimize plant power factor $9,560 $14,980 - $9,560
-
kW-mo/yr
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,290 $500 $2,740
55,950
kWh
$550
-
kW-mo/yr
- -
TOTAL RECOMMENDED $189,630 $25,480 $11,070
226,050
kWh
$11,860
-
kW-mo/yr
$33,360 $133,340
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs