ITAC Assessment: AM0572
ITAC logo
ITAC Assessment: AM0572
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Truck trailers
NAICS 336212: Truck Trailer Manufacturing
SIC 3715: Truck Trailers
Sales Range $50
M
to 100
M
# of Employees 200
Plant Area 272,000
ft2
Annual Production 324
pieces
Production Hrs. Annual 2,000
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $221,211 2,538,178
kWh
Electricity Demand $90,917 12,026
kW-mo/yr
Natural Gas $58,799 6,063
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,765 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,425

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $10,200 $34,000 $6,800
75,500
kWh
$3,400
-
kW-mo/yr
- -
02 2.7124: Make a practice of turning off lights when not needed $6,050 - $4,100
45,565
kWh
$1,950
-
kW-mo/yr
- -
03 2.8123: Pay utility bills on time $1,925 - - - $1,925 -
04 2.3212: Optimize plant power factor $1,200 $3,250 - $1,200
-
kW-mo/yr
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,025 $460 $260
2,900
kWh
$30
-
kW-mo/yr
- $735
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $800 $400 $530
5,900
kWh
$270
-
kW-mo/yr
- -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $725 $350 $485
5,400
kWh
$240
-
kW-mo/yr
- -
08 2.7124: Make a practice of turning off lights when not needed $500 - $500
5,560
kWh
- - -
09 3.6193: Install equipment (eg compactor) to reduce disposal costs $340 - - - - $340
TOTAL RECOMMENDED $22,765 $38,460 $12,675
140,825
kWh
$7,090
-
kW-mo/yr
$1,925 $1,075
TOTAL IMPLEMENTED $22,425 $38,460 $12,675
140,825
kWh
$7,090
-
kW-mo/yr
$1,925 $735
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs