ITAC Assessment: AM0540
ITAC logo
ITAC Assessment: AM0540
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Aluminum alkylate
NAICS 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing
SIC 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 300
Plant Area 40,000
ft2
Annual Production 121,254,244
lb
Production Hrs. Annual 8,640
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $7,728,000 105,401,568
kWh
Electricity Demand $760,968 156,648
kW-mo/yr
Electricity Fees $2,560 -
Natural Gas $11,971,656 1,845,780
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $845,470 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $845,470

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.2113: Repair or replace steam traps $700,000 $117,000 - - $700,000
-
MMBtu
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $97,610 $1,000 $830
12,400
kWh
$80
-
kW-mo/yr
- $96,700 -
03 2.2136: Install / repair insulation on steam lines $12,800 $3,000 - - $12,800
-
MMBtu
- -
04 2.7121: Utilize daylight whenever possible in lieu of artificial light $15,410 $5,000 $12,300
183,000
kWh
$3,110
-
kW-mo/yr
- - -
05 2.2135: Repair and eliminate steam leaks $12,850 $2,000 - - $12,850
-
MMBtu
- -
06 2.4314: Use synthetic lubricant $5,820 - $5,440
81,200
kWh
$380
-
kW-mo/yr
- - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $980 $715 $445
6,660
kWh
$40
-
kW-mo/yr
- - $495
TOTAL RECOMMENDED $845,470 $128,715 $19,015
283,260
kWh
$3,610
-
kW-mo/yr
$725,650
-
MMBtu
$96,700 $495
TOTAL IMPLEMENTED $845,470 $128,715 $19,015
283,260
kWh
$3,610
-
kW-mo/yr
$725,650
-
MMBtu
$96,700 $495
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs