Assessment Year | 2008 |
---|---|
Principal Product | Aluminum alkylate |
NAICS | 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing |
SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 300 |
Plant Area |
40,000
ft2
|
Annual Production | 121,254,244
lb
|
Production Hrs. Annual | 8,640
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $7,728,000 | 105,401,568 |
kWh
|
$0.073 |
Electricity Demand | $760,968 | 156,648 |
kW-mo/yr
|
$4.86 |
Electricity Fees | $2,560 | - |
|
- |
Natural Gas | $11,971,656 | 1,845,780 |
MMBtu
|
$6.49 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $845,470 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $845,470 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2113: Repair or replace steam traps | $700,000 | $117,000 | - | - |
$700,000
-
MMBtu
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $97,610 | $1,000 |
$830
12,400
kWh
|
$80
-
kW-mo/yr
|
- | $96,700 | - | |
03 | 2.2136: Install / repair insulation on steam lines | $12,800 | $3,000 | - | - |
$12,800
-
MMBtu
|
- | - | |
04 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $15,410 | $5,000 |
$12,300
183,000
kWh
|
$3,110
-
kW-mo/yr
|
- | - | - | |
05 | 2.2135: Repair and eliminate steam leaks | $12,850 | $2,000 | - | - |
$12,850
-
MMBtu
|
- | - | |
06 | 2.4314: Use synthetic lubricant | $5,820 | - |
$5,440
81,200
kWh
|
$380
-
kW-mo/yr
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $980 | $715 |
$445
6,660
kWh
|
$40
-
kW-mo/yr
|
- | - | $495 | |
TOTAL RECOMMENDED | $845,470 | $128,715 |
$19,015
283,260
kWh
|
$3,610
-
kW-mo/yr
|
$725,650
-
MMBtu
|
$96,700 | $495 | ||
TOTAL IMPLEMENTED | $845,470 | $128,715 |
$19,015
283,260
kWh
|
$3,610
-
kW-mo/yr
|
$725,650
-
MMBtu
|
$96,700 | $495 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs