ITAC Assessment: AM0412
ITAC logo
ITAC Assessment: AM0412
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Industrial organic chemical processing and distilling
NAICS
n/a
SIC 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 135
Plant Area
n/a
Annual Production 500,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,034,627 22,010,765
kWh
Electricity Demand $235,099 38,076
kW-mo/yr
Electricity Fees $5,880 -
Natural Gas $3,598,649 896,736
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,770,175 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $337,765

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.2121: Increase amount of condensate returned $596,000 $117,000 - - - - - - $596,000
-
Tgal
02 4.652: Replace existing equipment with more suitable substitutes $536,220 $248,400 - - - - $536,220 - -
03 2.3321: Use steam pressure reduction to generate power $144,000 $600,000 $120,000
2,770,000
kWh
$24,000
-
kW-mo/yr
- - - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $140,200 $5,100 - - - - - $140,200 -
05 2.3321: Use steam pressure reduction to generate power $106,000 $140,000 $88,000
2,000,000
kWh
$18,000
-
kW-mo/yr
- - - - -
06 2.2135: Repair and eliminate steam leaks $104,625 $11,800 - - $104,625
-
MMBtu
- - - -
07 2.4133: Use most efficient type of electric motors $60,150 $202,680 $43,050
1,001,610
kWh
$17,100
-
kW-mo/yr
- - - - -
08 2.2161: Optimize operation of multi-stage vacuum steam jets $32,540 $117,000 $(-3,340.0)
(-77,770)
kWh
$(-1,890.0)
-
kW-mo/yr
$17,170
-
MMBtu
- - - $20,600
-
Tgal
09 2.2113: Repair or replace steam traps $24,450 $1,375 - - $24,450
-
MMBtu
- - - -
10 2.4314: Use synthetic lubricant $8,430 - $6,030
140,235
kWh
$2,400
-
kW-mo/yr
- - - - -
11 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,100 $8,600 $7,100
166,000
kWh
- - - - - -
12 2.3212: Optimize plant power factor $6,560 - - $6,560
-
kW-mo/yr
- - - - -
13 3.7132: Reuse rags until completely soiled $2,120 - - - - $2,120
-
lb
- - -
14 2.7124: Make a practice of turning off lights when not needed $1,000 - $1,000
23,460
kWh
- - - - - -
15 2.7121: Utilize daylight whenever possible in lieu of artificial light $780 - $780
18,200
kWh
- - - - - -
TOTAL RECOMMENDED $1,770,175 $1,451,955 $262,620
6,041,735
kWh
$66,170
-
kW-mo/yr
$146,245
-
MMBtu
$2,120
-
lb
$536,220 $140,200 $616,600
-
Tgal
TOTAL IMPLEMENTED $337,765 $220,955 $44,830
1,043,270
kWh
$23,660
-
kW-mo/yr
$129,075
-
MMBtu
- - $140,200 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs