ITAC Assessment: AM0361
ITAC logo
ITAC Assessment: AM0361
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Candles
NAICS
n/a
SIC 3999: Manufacturing Industries, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 300
Plant Area 265,000
ft2
Annual Production 17,000,000
lb
Production Hrs. Annual 8,544
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $380,510 9,873,388
kWh
Electricity Demand $139,387 21,956
kW-mo/yr
Natural Gas $116,375 19,231
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $639,284 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 4.441: Install automatic packing equipment $576,720 $201,440 n/a - - - $576,720 - -
02 4.652: Replace existing equipment with more suitable substitutes $30,000 $2,905 n/a - - - - - $30,000
03 2.3212: Optimize plant power factor $20,600 $41,200 n/a - $20,600
-
kW-mo/yr
- - - -
04 2.7122: Disconnect ballasts $4,920 $600 n/a $2,810
115,182
kWh
$2,110
-
kW-mo/yr
- - - -
05 4.821: Pay bills on time to avoid late fees $4,274 - n/a - - - - $4,274 -
06 2.7122: Disconnect ballasts $1,930 $300 n/a $1,100
45,135
kWh
$830
-
kW-mo/yr
- - - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $410 $100 n/a $410
16,706
kWh
- - - - -
08 2.2136: Install / repair insulation on steam lines $430 $120 n/a - - $430
-
MMBtu
- - -
TOTAL RECOMMENDED $639,284 $246,665 $4,320
177,023
kWh
$23,540
-
kW-mo/yr
$430
-
MMBtu
$576,720 $4,274 $30,000
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs