| Assessment Year | 1999 |
|---|---|
| Principal Product | Gypsum wallboard |
| NAICS |
n/a
|
| SIC | 3275: Gypsum Products |
| Sales Range | $10 M to 50M |
| # of Employees | 120 |
| Plant Area |
270,000
ft2
|
| Annual Production | 340,000
thousand feet
|
| Production Hrs. Annual | 8,712
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $489,429 | 14,997,656 |
kWh
|
$0.033 |
| Electricity Demand | $154,663 | 23,619 |
kW-mo/yr
|
$6.55 |
| Electricity Fees | $1,800 | - |
|
- |
| Natural Gas | $1,634,208 | 707,428 |
MMBtu
|
$2.31 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $624,915 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $23,765 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $481,000 | $1,207,000 |
$336,000
10,500,000
kWh
|
$111,000
-
kW-mo/yr
|
$(-341,000.0)
-
MMBtu
|
- | - | - | $375,000 | |
| 02 | 3.5311: Recover and reuse waste material | $93,150 | $110,000 |
$(-50.0)
(-1,465)
kWh
|
- | - |
$17,000
-
lb
|
- | $76,200 | - | |
| 03 | 2.2511: Insulate bare equipment | $27,000 | $850 | - | - |
$27,000
-
MMBtu
|
- | - | - | - | |
| 04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $21,800 | - | - |
$21,800
-
kW-mo/yr
|
- | - | - | - | - | |
| 05 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,150 | $140 |
$670
2,052
kWh
|
$480
-
kW-mo/yr
|
- | - | - | - | - | |
| 06 | 2.7124: Make a practice of turning off lights when not needed | $610 | - |
$610
2,052
kWh
|
- | - | - | - | - | - | |
| 07 | 4.652: Replace existing equipment with more suitable substitutes | $205 | $250 |
$50
1,465
kWh
|
$15
-
kW-mo/yr
|
- | - | $140 | - | - | |
| TOTAL RECOMMENDED | $624,915 | $1,318,240 |
$337,280
10,504,104
kWh
|
$133,295
-
kW-mo/yr
|
$(-314,000.0)
-
MMBtu
|
$17,000
-
lb
|
$140 | $76,200 | $375,000 | ||
| TOTAL IMPLEMENTED | $23,765 | $390 |
$1,330
5,569
kWh
|
$22,295
-
kW-mo/yr
|
- | - | $140 | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs