| Assessment Year | 1997 |
|---|---|
| Principal Product | Carbon steel pipe |
| NAICS |
n/a
|
| SIC | 3317: Steel Pipe and Tubes |
| Sales Range | $50 M to 100M |
| # of Employees | 130 |
| Plant Area |
268,000
ft2
|
| Annual Production | 96,000
ton
|
| Production Hrs. Annual | 4,769
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $363,248 | 9,011,137 |
kWh
|
$0.040 |
| Electricity Demand | $226,098 | 36,725 |
kW-mo/yr
|
$6.16 |
| Electricity Fees | $3,262 | - |
|
- |
| Natural Gas | $20,159 | 3,854 |
MMBtu
|
$5.23 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $171,087 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $95,317 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 4.611: Begin a practice of predictive / preventative maintenance | $75,170 | $4,200 |
$2,780
63,892
kWh
|
- | - | $72,390 | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $81,500 | $9,300 |
$81,500
1,812,720
kWh
|
- | - | - | |
| 03 | 3.8132: Use less toxic and volatile solvent substitutes | $12,480 | $9,270 | - |
$12,480
-
gal
|
- | - | |
| 04 | 2.8123: Pay utility bills on time | $1,337 | - | - | - | $1,337 | - | |
| 05 | 2.4314: Use synthetic lubricant | $600 | - |
$600
13,189
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $171,087 | $22,770 |
$84,880
1,889,801
kWh
|
$12,480
-
gal
|
$1,337 | $72,390 | ||
| TOTAL IMPLEMENTED | $95,317 | $18,570 |
$81,500
1,812,720
kWh
|
$12,480
-
gal
|
$1,337 | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs