Assessment Year | 1997 |
---|---|
Principal Product | Oilfield service equipment |
NAICS |
n/a
|
SIC | 3533: Oil and Gas Field Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
128,800
ft2
|
Annual Production | 7,200
pieces
|
Production Hrs. Annual | 8,208
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $273,343 | 5,084,994 |
kWh
|
$0.054 |
Electricity Demand | $71,937 | 11,158 |
kW-mo/yr
|
$6.45 |
Electricity Fees | $29,023 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,230 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,890 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3134: Shift from daytime to nighttime operation | $13,800 | - | - |
$13,800
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.8123: Pay utility bills on time | $4,280 | - | - | - | $4,280 | - | - | - | |
03 | 2.7124: Make a practice of turning off lights when not needed | $1,490 | - |
$490
22,274
kWh
|
$1,000
-
kW-mo/yr
|
- | - | - | - | |
04 | 4.211: Consider use / purchase of bulk materials where possible | $1,300 | - | - | - | - | - | - | $1,300 | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $680 | $300 |
$680
31,067
kWh
|
- | - | - | - | - | |
06 | 3.6194: Ship hydraulic oil to secondary fuel program | $240 | - | - | - | - |
$240
-
gal
|
- | - | |
07 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $440 | - | - | - | - | - |
$440
-
lb
|
- | |
TOTAL RECOMMENDED | $22,230 | $300 |
$1,170
53,341
kWh
|
$14,800
-
kW-mo/yr
|
$4,280 |
$240
-
gal
|
$440
-
lb
|
$1,300 | ||
TOTAL IMPLEMENTED | $6,890 | $300 |
$1,170
53,341
kWh
|
$1,000
-
kW-mo/yr
|
$4,280 | - |
$440
-
lb
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs