ITAC Assessment: AM0224
ITAC logo
ITAC Assessment: AM0224
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Rubber balloons, mylar balloons, kites
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 70
Plant Area 131,000
ft2
Annual Production 132,000,000
pieces
Production Hrs. Annual 6,744
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $94,789 1,435,229
kWh
Natural Gas $57,904 10,612
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,940 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,940

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,090 $1,000 $6,090
219,226
kWh
02 2.7121: Utilize daylight whenever possible in lieu of artificial light $425 - $425
2,931
kWh
03 2.2511: Insulate bare equipment $355 $126 $355
6,741
kWh
04 2.7142: Utilize higher efficiency lamps and/or ballasts $70 $26 $70
586
kWh
TOTAL RECOMMENDED $6,940 $1,152 $6,940
229,484
kWh
TOTAL IMPLEMENTED $6,940 $1,152 $6,940
229,484
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs