Assessment Year | 1994 |
---|---|
Principal Product | Molded rubber products for the oil field and automotive indu |
NAICS |
n/a
|
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
121,000
ft2
|
Annual Production | 1,600,000
lb
|
Production Hrs. Annual | 8,424
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $600,535 | 11,684,350 |
kWh
|
$0.051 |
Natural Gas | $65,927 | 18,457 |
MMBtu
|
$3.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $51,269 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $35,749 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $30,189 | $38,000 | - | - | $30,189 | |
02 | 2.2121: Increase amount of condensate returned | $10,905 | $2,800 | - |
$10,905
-
MMBtu
|
- | |
03 | 2.6224: Schedule baking times of small and large components | $4,340 | - |
$4,340
-
kWh
|
- | - | |
04 | 2.7124: Make a practice of turning off lights when not needed | $1,510 | - |
$1,510
44,256
kWh
|
- | - | |
05 | 2.8114: Change rate schedules or other changes in utility service | $4,050 | $2,500 | - | - | $4,050 | |
06 | 2.2122: Install / repair insulation on condensate lines | $275 | $200 | - |
$275
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $51,269 | $43,500 |
$5,850
44,256
kWh
|
$11,180
-
MMBtu
|
$34,239 | ||
TOTAL IMPLEMENTED | $35,749 | $40,500 |
$1,510
44,256
kWh
|
- | $34,239 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs