ITAC Assessment: AM0169
ITAC logo
ITAC Assessment: AM0169
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product oil and gas drilling equipment
NAICS
n/a
SIC 3533: Oil and Gas Field Machinery and Equipment
Sales Range $50
M
to 100
M
# of Employees 50
Plant Area 22,000
ft2
Annual Production 800
pieces
Production Hrs. Annual 4,976
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $117,980 1,454,279
kWh
Natural Gas $544 82
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,489 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,129

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.3212: Optimize plant power factor $3,000 $14,000 $3,000
-
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $319 - $319
15,240
kWh
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $810 $2,000 $810
15,533
kWh
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $820 $1,700 $820
15,826
kWh
05 2.8123: Pay utility bills on time $540 - $540
-
kWh
TOTAL RECOMMENDED $5,489 $17,700 $5,489
46,599
kWh
TOTAL IMPLEMENTED $1,129 $2,000 $1,129
30,773
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs