| Assessment Year | 1988 |
|---|---|
| Principal Product | MANUFACTURED HOUSING |
| NAICS |
n/a
|
| SIC | 2451: Mobile Homes |
| Sales Range | $10 M to 50M |
| # of Employees | 104 |
| Plant Area |
n/a
|
| Annual Production | 750
pieces
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $36,465 | 519,637 |
kWh
|
$0.070 |
| Natural Gas | $1,544 | 412 |
MMBtu
|
$3.75 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $3,289 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,484 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $520 | $188 |
$520
6,741
kWh
|
- | |
| 02 | 2.7111: Reduce illumination to minimum necessary levels | $1,120 | $500 |
$1,120
16,413
kWh
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $600 | $300 |
$600
12,016
kWh
|
- | |
| 04 | 2.2437: Recover waste heat from equipment | $340 | $550 | - |
$340
-
MMBtu
|
|
| 05 | 2.2443: Re-use or recycle hot or cold process exhaust air | $300 | $600 |
$300
2,345
kWh
|
- | |
| 06 | 2.6212: Turn off equipment during breaks, reduce operating time | $210 | - |
$210
4,103
kWh
|
- | |
| 07 | 2.8114: Change rate schedules or other changes in utility service | $165 | $625 |
$165
3,224
kWh
|
- | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $34 | $100 |
$34
586
kWh
|
- | |
| TOTAL RECOMMENDED | $3,289 | $2,863 |
$2,949
45,428
kWh
|
$340
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $2,484 | $1,088 |
$2,484
39,859
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs