ITAC Assessment: AM0008
ITAC logo
ITAC Assessment: AM0008
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product WOODEN PALLETS,VENEERS
NAICS
n/a
SIC 2448: Wood Pallets and Skids
Sales Range $1
M
to 5
M
# of Employees 50
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 2,080
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $78,950 839,683
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,665 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,214

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $204 $624 $204
2,931
kWh
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $50 $5 $50
1,758
kWh
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $960 $1,580 $960
31,360
kWh
04 2.5194: Redesign process $8,451 $14,300 $8,451
204,279
kWh
TOTAL RECOMMENDED $9,665 $16,509 $9,665
240,328
kWh
TOTAL IMPLEMENTED $1,214 $2,209 $1,214
36,049
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs