Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,123

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
WV0360 #03 Y:2007 Utilize higher efficiency lamps and/or ballasts $31,939 $70,000
WV0360 #02 Y:2007 Change product design to reduce energy requirements $44,169 $15,000
WV0360 #01 Y:2007 Adjust burners for efficient operation $48,535 $170,000
MZ0003 #06 Y:2007 Add area lighting switches $3,995 $500
MZ0003 #05 Y:2007 Install occupancy sensors $5,992 $2,950
MZ0003 #04 Y:2007 Disconnect ballasts $45,032 $4,012
MZ0003 #03 Y:2007 Use waste heat from hot flue gases to preheat $23,859 $30,000
MZ0003 #02 Y:2007 Use adjustable frequency drive or multiple speed motors on existing system $56,702 $7,764
MZ0003 #01 Y:2007 Replace boiler $237,208 $220,000
SD0395 #06 Y:2007 Use adjustable frequency drive or multiple speed motors on existing system $659 $1,146
SD0395 #05 Y:2007 Install occupancy sensors $3,878 $3,400
SD0395 #04 Y:2007 Recover waste heat from equipment $4,081 $1,213
SD0395 #03 Y:2007 Eliminate leaks in inert gas and compressed air lines/ valves $5,155 $240
SD0395 #02 Y:2007 Replace electrically-operated equipment with fossil fuel equipment $5,658 $13,350
SD0395 #01 Y:2007 Use adjustable frequency drive or multiple speed motors on existing system $10,816 $8,425
OK0747 #07 Y:2007 Begin a practice of predictive / preventative maintenance $2,068 $200
OK0747 #06 Y:2007 Install skylights $22,903 $139,000
OK0747 #05 Y:2007 Use solar heat for heat $14,978 $138,320
OK0747 #04 Y:2007 Reschedule plant operations or reduce load to avoid peaks $7,099 -
OK0747 #03 Y:2007 Reduce the pressure of compressed air to the minimum required $1,756 -