| WV0360 #03 Y:2007 | 03 | 2007 | Utilize higher efficiency lamps and/or ballasts | $31,939 | $70,000 | |
| WV0360 #02 Y:2007 | 02 | 2007 | Change product design to reduce energy requirements | $44,169 | $15,000 | |
| WV0360 #01 Y:2007 | 01 | 2007 | Adjust burners for efficient operation | $48,535 | $170,000 | |
| MZ0003 #06 Y:2007 | 06 | 2007 | Add area lighting switches | $3,995 | $500 | |
| MZ0003 #05 Y:2007 | 05 | 2007 | Install occupancy sensors | $5,992 | $2,950 | |
| MZ0003 #04 Y:2007 | 04 | 2007 | Disconnect ballasts | $45,032 | $4,012 | |
| MZ0003 #03 Y:2007 | 03 | 2007 | Use waste heat from hot flue gases to preheat | $23,859 | $30,000 | |
| MZ0003 #02 Y:2007 | 02 | 2007 | Use adjustable frequency drive or multiple speed motors on existing system | $56,702 | $7,764 | |
| MZ0003 #01 Y:2007 | 01 | 2007 | Replace boiler | $237,208 | $220,000 | |
| SD0395 #06 Y:2007 | 06 | 2007 | Use adjustable frequency drive or multiple speed motors on existing system | $659 | $1,146 | |
| SD0395 #05 Y:2007 | 05 | 2007 | Install occupancy sensors | $3,878 | $3,400 | |
| SD0395 #04 Y:2007 | 04 | 2007 | Recover waste heat from equipment | $4,081 | $1,213 | |
| SD0395 #03 Y:2007 | 03 | 2007 | Eliminate leaks in inert gas and compressed air lines/ valves | $5,155 | $240 | |
| SD0395 #02 Y:2007 | 02 | 2007 | Replace electrically-operated equipment with fossil fuel equipment | $5,658 | $13,350 | |
| SD0395 #01 Y:2007 | 01 | 2007 | Use adjustable frequency drive or multiple speed motors on existing system | $10,816 | $8,425 | |
| OK0747 #07 Y:2007 | 07 | 2007 | Begin a practice of predictive / preventative maintenance | $2,068 | $200 | |
| OK0747 #06 Y:2007 | 06 | 2007 | Install skylights | $22,903 | $139,000 | |
| OK0747 #05 Y:2007 | 05 | 2007 | Use solar heat for heat | $14,978 | $138,320 | |
| OK0747 #04 Y:2007 | 04 | 2007 | Reschedule plant operations or reduce load to avoid peaks | $7,099 | - | |
| OK0747 #03 Y:2007 | 03 | 2007 | Reduce the pressure of compressed air to the minimum required | $1,756 | - |