| MI0473 #06 Y:2026 | 06 | 2026 | Clean or color roof to reduce solar load | $5,599 | $23,200 |
n/a
|
| MI0473 #05 Y:2026 | 05 | 2026 | Install vinyl strip / high speed / air curtain doors | $625 | $1,200 |
n/a
|
| MI0473 #04 Y:2026 | 04 | 2026 | Turn off equipment when not in use | $2,046 | $2,600 |
n/a
|
| MI0473 #03 Y:2026 | 03 | 2026 | Use separate switches on perimeter lighting which may be turned off when natural light is available | $253 | $80 |
n/a
|
| MI0473 #02 Y:2026 | 02 | 2026 | Eliminate leaks in inert gas and compressed air lines/ valves | $7,098 | $1,980 |
n/a
|
| MI0473 #01 Y:2026 | 01 | 2026 | Use power during off-peak periods | $3,799 | - |
n/a
|
| UF0647 #12 Y:2026 | 12 | 2026 | Re-arrange equipment layout to reduce labor costs | $5,628 | $1,368 |
n/a
|
| UF0647 #11 Y:2026 | 11 | 2026 | Optimize production lot sizes and inventories | $22,000 | $4,000 |
n/a
|
| UF0647 #10 Y:2026 | 10 | 2026 | Initiate a total quality management program | $50,000 | $85,000 |
n/a
|
| UF0647 #09 Y:2026 | 09 | 2026 | Automate finishing process | $242,080 | $200,000 |
n/a
|
| UF0647 #08 Y:2026 | 08 | 2026 | Utilize controls to operate equipment only when needed | $369 | $900 |
n/a
|
| UF0647 #07 Y:2026 | 07 | 2026 | Reduce the pressure of compressed air to the minimum required | $377 | - |
n/a
|
| UF0647 #06 Y:2026 | 06 | 2026 | Utilize energy-efficient belts and other improved mechanisms | $442 | - |
n/a
|
| UF0647 #05 Y:2026 | 05 | 2026 | Use / purchase optimum sized compressor | $1,056 | $2,800 |
n/a
|
| UF0647 #04 Y:2026 | 04 | 2026 | Isolate hot or cold equipment | $7,455 | $28,000 |
n/a
|
| UF0647 #03 Y:2026 | 03 | 2026 | Utilize sensors controlling roof and wall openings | $8,168 | $4,000 |
n/a
|
| UF0647 #02 Y:2026 | 02 | 2026 | Use demand controller or load shedder | $19,310 | $12,418 |
n/a
|
| UF0647 #01 Y:2026 | 01 | 2026 | Use or replace with energy efficient substitutes | $75,479 | $250,000 |
n/a
|
| UF0646 #11 Y:2026 | 11 | 2026 | Level two – install control system using iiot devices with communication capabilities to store data to the cloud | $4,169 | $15,000 |
n/a
|
| UF0646 #10 Y:2026 | 10 | 2026 | Improve space comfort conditioning | $45,534 | $22,638 |