261
matching recommendations
$
$
| ARC | 2+ Digits Required | |
| NAICS | 3+ Digits Required | |
| SIC | 2+ Digits Required | |
| 3+ Characters Required for Products | ||
| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| UL2516 #08 Y:2025 | 08 | 2025 | Install occupancy sensors | $149 | $254 |
n/a
|
| UL2516 #07 Y:2025 | 07 | 2025 | Utilize higher efficiency lamps and/or ballasts | $49,312 | $34,242 |
n/a
|
| UL2516 #06 Y:2025 | 06 | 2025 | Use adjustable frequency drive or multiple speed motors on existing system | $3,831 | $3,900 |
n/a
|
| UL2516 #05 Y:2025 | 05 | 2025 | Use solar heat to make electricty | $135,359 | $916,268 |
n/a
|
| UL2516 #04 Y:2025 | 04 | 2025 | Change rate schedules or other changes in utility service | $43,408 | - |
n/a
|
| UL2516 #03 Y:2025 | 03 | 2025 | Optimize plant power factor | $2,217 | $10,400 |
n/a
|
| UL2516 #02 Y:2025 | 02 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $15,881 | $3,780 |
n/a
|
| UL2516 #01 Y:2025 | 01 | 2025 | Reduce the pressure of compressed air to the minimum required | $8,018 | - |
n/a
|
| UL2513 #06 Y:2025 | 06 | 2025 | Install occupancy sensors | $602 | $2,234 |
n/a
|
| UL2513 #05 Y:2025 | 05 | 2025 | Utilize higher efficiency lamps and/or ballasts | $1,723 | $561 |
n/a
|
| UL2513 #04 Y:2025 | 04 | 2025 | Use solar heat to make electricty | $57,929 | $431,966 |
n/a
|
| UL2513 #03 Y:2025 | 03 | 2025 | Use outside cold water source as a supply of cooling water | $34,574 | $58,425 |
n/a
|
| UL2513 #02 Y:2025 | 02 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $2,535 | $1,080 |
n/a
|
| UL2513 #01 Y:2025 | 01 | 2025 | Reduce the pressure of compressed air to the minimum required | $1,366 | - |
n/a
|
| UL2510 #04 Y:2025 | 04 | 2025 | Install occupancy sensors | $1,506 | $185 |
n/a
|
| UL2510 #03 Y:2025 | 03 | 2025 | Use adjustable frequency drive or multiple speed motors on existing system | $4,413 | $9,750 |
n/a
|
| UL2510 #02 Y:2025 | 02 | 2025 | Use solar heat to make electricty | $71,181 | $417,175 |
n/a
|
| UL2510 #01 Y:2025 | 01 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $3,769 | $3,240 |
n/a
|
| UL2505 #04 Y:2025 | 04 | 2025 | Use optimum thickness insulation | $23,183 | $32,000 |
n/a
|
| UL2505 #03 Y:2025 | 03 | 2025 | Recover waste heat from equipment | $14,289 | $39,000 |
n/a
|