Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

20

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Secondary smelting and refining of nonferrous
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
OK0533 #06 Y:1997 Install occupancy sensors $390 $660
OK0533 #05 Y:1997 Contract a wood pallet recycling company $750 -
OK0533 #04 Y:1997 Turn off equipment when not in use $3,426 -
OK0533 #03 Y:1997 Replace city water with recycled water via cooling tower $11,845 $8,350
OK0533 #02 Y:1997 Use waste heat from hot flue gases to preheat $14,444 $17,000
OK0533 #01 Y:1997 Move product using mechanical means $22,960 $110,000
OK0356 #07 Y:1991 Utilize higher efficiency lamps and/or ballasts $3,095 -
OK0356 #06 Y:1991 Utilize energy-efficient belts and other improved mechanisms $4,152 -
OK0356 #05 Y:1991 Eliminate leaks in inert gas and compressed air lines/ valves $1,377 -
OK0356 #04 Y:1991 Reduce the pressure of compressed air to the minimum required $1,311 -
OK0356 #03 Y:1991 Use adjustable frequency drive or multiple speed motors on existing system $60,081 $58,228
OK0356 #02 Y:1991 Install timers and/or thermostats $254 $360
OK0356 #01 Y:1991 Utilize higher efficiency lamps and/or ballasts $534 -
OK0109 #07 Y:1983 Install timers and/or thermostats $341 $500
OK0109 #06 Y:1983 Analyze flue gas for proper air/fuel ratio $62,013 $800
OK0109 #05 Y:1983 Use most efficient type of electric motors $450 $1,339
OK0109 #04 Y:1983 Utilize energy-efficient belts and other improved mechanisms $83 -
OK0109 #03 Y:1983 Utilize higher efficiency lamps and/or ballasts $205 $340
OK0109 #02 Y:1983 Utilize higher efficiency lamps and/or ballasts $2,453 $10,800
OK0109 #01 Y:1983 Utilize higher efficiency lamps and/or ballasts $661 $411